Wiest-Levy method
Contents |
[edit] Introduction
The Wiest-Levy method is a critical path method (CPM) based on the deterministic or exact duration of each task. CPM was developed by Morgan R Walker of the Engineering Services Division at Du Pont, and James E Kelley, who worked at Remington Rand. Walker and Kelly were interested in improving scheduling techniques used in the construction of industrial plants.
The Wiest-Levy method is a practical approach to problem solving that can be applied to ecision making. It sets out a way of deciding which jobs or activities involved in a complex project are higher priority (or critical) based on their overall impact. It also attempts to devise the ideal schedule for all jobs and resources required to meet time and budget targets.
[edit] History
Named after the American academics, Jerome D Wiest and Ferdinand K Levy, the Wiest-Levy method was introduced in the mid-1960s. A third collaborator, Gerald L Thompson was also involved in the development of this technique used to analyse, plan and schedule large, complex projects.
When applied to resource allocation and other aspects of project management in construction, this method helps to optimise the sequence of activities. Wiest created a concept called SPAR (Scheduling Program for Allocating Resources) which can be used for scheduling projects that have limited resources.
In the case of non-critical activities, the one that solves the problem with the least delay is chosen. If there are two activities with the same conditions, the one with the greatest leeway is delayed first, meaning that critical activities are only delayed when there is no other option.
For more information see: Critical path method.
[edit] Related articles on Designing Buildings Wiki
- Critical path method CPM.
- Progress of construction works.
- Resource leveling.
- Resource allocation in design and construction.
- Scheduling construction activities.
[edit] External resources
- F K Levy, G L Thompson and J D Wiest, Harvard Business Review, The ABCs of the Critical Path Method (September 1963).
Featured articles and news
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.