Wiest-Levy method
Contents |
[edit] Introduction
The Wiest-Levy method is a critical path method (CPM) based on the deterministic or exact duration of each task. CPM was developed by Morgan R Walker of the Engineering Services Division at Du Pont, and James E Kelley, who worked at Remington Rand. Walker and Kelly were interested in improving scheduling techniques used in the construction of industrial plants.
The Wiest-Levy method is a practical approach to problem solving that can be applied to ecision making. It sets out a way of deciding which jobs or activities involved in a complex project are higher priority (or critical) based on their overall impact. It also attempts to devise the ideal schedule for all jobs and resources required to meet time and budget targets.
[edit] History
Named after the American academics, Jerome D Wiest and Ferdinand K Levy, the Wiest-Levy method was introduced in the mid-1960s. A third collaborator, Gerald L Thompson was also involved in the development of this technique used to analyse, plan and schedule large, complex projects.
When applied to resource allocation and other aspects of project management in construction, this method helps to optimise the sequence of activities. Wiest created a concept called SPAR (Scheduling Program for Allocating Resources) which can be used for scheduling projects that have limited resources.
In the case of non-critical activities, the one that solves the problem with the least delay is chosen. If there are two activities with the same conditions, the one with the greatest leeway is delayed first, meaning that critical activities are only delayed when there is no other option.
For more information see: Critical path method.
[edit] Related articles on Designing Buildings Wiki
- Critical path method CPM.
- Progress of construction works.
- Resource leveling.
- Resource allocation in design and construction.
- Scheduling construction activities.
[edit] External resources
- F K Levy, G L Thompson and J D Wiest, Harvard Business Review, The ABCs of the Critical Path Method (September 1963).
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
The role of the client and decision making
CIOB response to built environment professions call for evidence.
Construction's sustainability reporting revolution
Tracking upfront embodied carbon with digital tools.
ECA welcomes procurement reforms
Public spending must back British jobs and skills.
Campaigning for Edinburgh: the Cockburn Association 1875-2049
The role of the civic voice in protecting character. Book review.
CIOB photography competition is open for entries.
ECA Edmundson apprentice of the year award
Finalists announced.
Major new study exposes serious knowledge gaps.
Generating energy from internal light as well as sunshine.
ECA welcomes plans to strengthen subcontractor quality control.
Combining mid-career qualifications with experience broadens career opportunities.
Why being a mentor can help your career.
Channel 4 broadcaster to host 125th anniversary ceremony.